Connection to the power supply system
Scheduled outages

INFORMATION for legal entities and individual entrepreneurs on the issue of connecting electrical installations to the electric networks of the Vitebsk branch electric networks with a total capacity of up to 250 kVA according to the “one window” principle

The list of documents and (or) information submitted by interested parties to the authorized body for the implementation of the administrative procedure:

  • statement (electrical network)
  • project documentation (heating networks)
  • design documentation

Duration of the administrative procedure:
7 days

Validity of certificates or other documents issued during the administrative procedure:
the duration of the works

The size of the fees charged during the administrative procedure:
free

INFORMATION for legal entities and individual entrepreneurs on the issue of connecting electrical installations to the electric networks of the Vitebsk branch electric networks with a total capacity of up to 250 kVA according to the “one window” principle

The list of documents and (or) information submitted by interested parties to the authorized body for the implementation of the administrative procedure:

  • a statement in the prescribed form
  • sections of project documentation for internal and external networks and systems in terms of power supply, the internal part of the engineering equipment in the electrical, lighting, including all the necessary calculations and the information (on paper and electronic media) 
  • a copy of the technical readiness of the act of electrical work 
  • information about the organization of the operation of electrical 
  • electric power consumption rates per unit of production (works, services) or limits the consumption of electric energy, approved in the established order (in cases stipulated by law) 
  • written application about the contractual terms of active power and energy consumption broken down by settlement period (month) 
  • instructions defining operation modes of power station (in the case of connection to the electricity network with electrical power station) 
  • connection utility power station to the electrical network for parallel operation with the power system (under a single operative control) (in the case of connection to the electricity network with electrical power station) 
  • a copy of a title (title certificates) document on the power facility or the land on which it is planned to place the object of power (in the case where technical specifications were issued as part of the licensing documentation for construction), a copy of a title (title certificates) document on the power facility (in the case of a change of ownership ( the owner) the object of power, if it does not require any changes in the category of power supply reliability, increase the resolution to ispolz Hovhan power change of attachment points) 
  • a document confirming payment of the fee 

If necessary, the connection to the electrical mains transit in the manner specified in paragraph 74 of the Rules of electricity, additionally submit: 

  • written consent of the transit of electric network owner, a legal entity of the Republic of Belarus or an individual entrepreneur, on the connection of electrical installations of the legal entity or individual entrepreneur to being in his property, economic management or operational management of the electrical network (in the case of connection of electrical installations of legal entities and individual entrepreneurs to the mains ) 
  • a copy of the act of differentiation balance accessory electrical grids (electrical) and the operational responsibilities of the parties drawn up by the owner of the electrical network, which is a legal entity of the Republic of Belarus or an individual entrepreneur or a legal entity, individual entrepreneur, electrical systems which are connected to the mains power supply organization, part of PA " Belenergo "indirectly (through transit electric networks)
  • copy of the agreement on the transit of electricity (capacity) between the owner of the transit of electricity network, a legal entity of the Republic of Belarus or an individual entrepreneur or a legal entity, individual entrepreneur, electrical systems which are connected to the mains power supply organization, part of the "Belenergo" indirectly (through transit electric networks)

If necessary, the connection to the mains power supply company, part of the "Belenergo" with electrical block stations additionally presented: 

  • written application of contractual values ​​of active power and energy consumption, by calculation period (month) of separate structural units holder unit station if necessary transmit separate structural units holder unit station electric energy generated by a block station, on electrical networks power supplying organization affiliated of the "Belenergo" 
  • delivery schedule (for the purposes of sale) to the mains power supply organization, part of the "Belenergo", the electrical energy generated by power stations (with the exception of generating plants using renewable energy sources), by settlement period (month) and times of the day (night minimum load power system - from 23.00 to 6.00 hours daily maximum load power system and the rest of the day) in case the applicant's intentions (the owner of power stations) to supply (for the sale) in Electrical eskuyu network power supply company, part of the "Belenergo" electrical energy generated block station 
  • schedule transmission of separate structural units holder unit station electric energy generated by a block station, by the mains power supply company, part of the "Belenergo", by calculation period (month) in cases applicant's intention (holder unit station) transmit separate structural units holder unit station electric energy generated block station on the mains power supply company, part of the "Belenergo" 
  • transit flow chart of electric energy generated by a block station, by calculation period (month) in cases applicant's intention (holder unit station) to implement flow transit 
  • documents confirming the production of power station electricity in cogeneration mode and (or) tri-generation (with the exception of the block-stations operating on local fuels, renewable energy sources and secondary energy resources), in case the applicant's intentions (the owner of power stations) supply (for purposes of sale) to the mains power supply company, part of the "Belenergo" electrical energy generated block station 
  • Typical DSA hourly schedules hourly values ​​of active power electricity generation unit station, issuing of active power into the mains power supply company, part of the "Belenergo" active power consumption of the electric network power supply company, part of the "Belenergo" for weekday and weekend typical DSA hourly schedules transmission autonomous structural units holder unit station electric energy generated block Art ntsiey at the mains power supply company, part of the "Belenergo" and (or) in cases of flow transit applicant's intention (holder unit station) to transmit separate structural units holder unit station electric energy generated block station,

When viewed on the electrical power facility additionally presented: 

  • set of acceptance documentation for the installation of electrical installations 
  • a set of documents to carry out commissioning work
  • records the electrical measurement and test

If you change the owner (owner) of the object of power, if it does not require any changes in the category of power supply reliability, increase the resolution to use the power, change of connection points are represented: 

  • a copy of the constituent documents (for legal entities of the Republic of Belarus) 
  • a copy of the document confirming the state registration of the legal entity or individual entrepreneur 
  • copy of the contract under the terms of which the foreign organization on the territory of the Republic of Belarus performs works and (or) providing services, carries out other activities not prohibited by law (for foreign companies) 
  • copy of the permit to open a representative (for foreign organizations offices) 
  • power of attorney or other document confirming the authority of foreign organization on the territory of the Republic of Belarus for transactions and other legal actions on behalf of foreign organizations, including the powers to represent its interests in relations governed by the Rules of electricity (for representative offices of foreign companies)

For temporary connection to conduct commissioning works on the project of power supply scheme are presented: 

  • statement 
  • sections of project documentation for internal and external networks and systems in terms of power supply, the internal part of the engineering equipment in the electrical, lighting, including all the necessary calculations and the information (on paper and electronic media) 
  • a copy of the technical readiness of the act of electrical work 
  • information about the organization of the operation of electrical

The duration of the administrative procedure:
20 days for multi-dwelling buildings (with the exception of multi-dwelling houses built on government orders, as well as apartment houses, where all the dwellings are dwellings commercial use of the public housing stock and social use) - 10 days

Validity of certificates or other documents issued during the administrative procedure:
indefinitely

The size of the fees charged during the administrative procedure:

issuance of an act of differentiation of carrying supplies of electrical networks (electrical) and the operational responsibilities of the parties

1.5 the base value

inspection of electrical installations with the registration certificate of electrical inspection

3 baselines

checking means oplombirovka parameterization and the estimated distribution of electric energy (power)

1.5 the base value  

Finally, power supply contract

is free

direct electrical connection

2.5 the base value

Body (organization) authorized to conduct the administrative procedure: 

Vitebsk heat network

The list of documents and (or) information submitted by interested parties to the authorized body for the implementation of the administrative procedure:

  • a statement in the prescribed form
  • a copy of the title document to the site with the exception of multi-family residential buildings, construction of residential buildings in which was carried out on the basis of agreements to create objects of shared construction contracts, provides for the construction of residential premises as part of the developers organizations, as well as on the basis of concluded between developers - issuers and individuals contracts ( agreements), providing issuers obligations for the construction of residential premises in apartment buildings owners mi housing bonds)

The duration of the administrative procedure:
20 days for multi-dwelling buildings (with the exception of multi-dwelling houses built on government orders, as well as apartment houses, where all the dwellings are dwellings commercial use of public housing and social use) - 10 days

Validity of certificates or other documents issued during the administrative procedure:
indefinitely

The size of the fees charged during the administrative procedure:
according to the price list